Projects

Rotork Actuators Installations at Total Plaisance (JUHI)

Rotork Actuators Installations at Total Plaisance

Rotork Actuators Installations at Total Plaisance

Year of Completion: 2016
Site: Plaisance
Client: Total

JUHI Airport.

The project consisted of unwiring old actuators and removing them from the valves using a crane as they each weigh more than 600kg. Adapters were then designed to fit the new Rotork actuator to the valve. After fitting the adapters, the actuator were placed using the crane, bolted, wired, configured and commissioned.

New Boiler Installation for Medine S.E

New Boiler Installation for Medine S.E

New Boiler Installation for Medine S.E

Year of Completion: 2015
Site: Medine
Client: Medine S.E

A 75 ton boiler was moved from the Old Union St. Aubin factory to Medine for which ECS was solicited for its automation and instrumentation system.

CTDS Variable Speed Drive Replacement

CTDS Variable Speed Drive Replacement

CTDS Variable Speed Drive Replacement

Year of Completion: 2015
Site: Saint Aubin
Client: OTEOSAL

CTDS Control Room.

The project consisted of replacing the existing VSDs with new ones to match the power rating of new motors installed. Modification to the PLC programming was done to accommodate the control of 4 new VSDs and rotation detectors.

CTDS Ash Combustor System

CTDS Ash Combustor System

CTDS Ash Combustor System

Year of Completion: 2015
Site: Saint Aubin
Client: OTEOSAL

Installation of Cable tray, Power cables and Instrumentation Cables.

The project consisted of promoting effective carbon post-combustion and at the same time bottom ash extraction with the ultimate target of reducing the carbon in ash levels below the threshold required for ash re-use. Automation of the new Ash Post Combustor system installed by Magaldi Group was implemented by ECS.

Automation of Energy Plant at Omnicane

Automation of Energy Plant at Omnicane

Year of Completion: 2014
Site: Savannah
Client: Omnicane

ECS worked with Thermax from India for the implementation, testing and commissioning of the boiler. For the auxiliary installations, ECS was responsible for the whole automation work. The automation system of the plant is based on the Siemens S7-300 PLCs with WinCC as operator interface.

This project consisted of the design and implementation of a control system

Automation of a Core Sampler Prototype for EU

Automation of a Core Sampler Prototype for EU

Year of Completion: 2013
Site: Kenya
Client: South Nyanza Sugar Company

This project consisted of the design and implementation of a control system for a prototype core sampler for sugar cane. The project was financed by the EU and the final client was SONY sugar. The design is based on a Schneider Twido PLC with Magelis Operator panel.

Electrical and Instrumentation Works for Meaders

Electrical and Instrumentation Works for Meaders

Electrical and Instrumentation Works for Meaders

 The installation of cable trays, power cables, instrumentation cables and control panels was done by ECS. Assistance to testing and commissioning was also provided.

Energy Monitoring in Constance Hotels

Energy Monitoring in Constance Hotels

Energy Monitoring in Constance Hotels

Year of Completion: 2013
Site: Mauritius, Maldives. Seychelles
Client: Constance Group of Hotels/service/building-management-systems

ECS has installed the energy monitoring and reporting system in all the six hotels of Constance group.

ECS provided the client with an online support which facilitates the rapid diagnostics of system problem if any and also to add new equipment to the system network. In this way a cost effective solution is provided to the client in terms of labour.

Instrumentation and Control Works at Omnicane Ethanol Plant

Instrumentation and Control Works at Omnicane Ethanol Plant

Instrumentation and Control Works at Omnicane Ethanol Plant

Year of Completion: 2013
Site: Savannah
Client: Omnicane

ECS did the whole installation for the Fermentation.

The distillery and evaporators include the Evaporator plant, Balance of Plant, Distillery and Alcohol tank farm. The control system is based on an ABB AC800F controller with remote IOs on profibus.

Upgrading of PLC at SOSUMO

Upgrading of PLC at SOSUMO

Upgrading of PLC at SOSUMO

Year of Completion: 2012
Site: Burundi
Client: SOSUMO

 ECS supervised the installation of the whole system, also performed the testing and commissioning. Training of the operators was done during the testing and commissioning phases. A training on programming of the Schneider PLC and Magelis Operator interface was also carried out for the engineers and technicians. The boiler process loops programming were also explained to the engineers and technicians.

Where are WE

Keep in Touch

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Electrical & Control Specialists Ltd

Office:
Mon Loisir Industrial Zone
Riviere du Rempart

Phone: (230) 260 0862

Email: ecs@ecs.mu